upcoming events

Jul 2019
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Survey

1. What do you consider the largest Risk for your company?

2. What are the Risk Mitigation Strategies you apply?

Submit

Galleries

This event is open for all professionals interested or currently working in Starups in Hanoi, or supply chai professionals in Hanoi, or who are interested in looking for business collaboration for U.S. market through meeting with a delegation of Baylor University (U.S.), Executive Master Program.

CAREER OPPORTUNITIES

PURCHASING MANAGER - DETMOLD PACKAGING

Involved in carry out, application and maintenance of the company processing system.

FAR EAST PLANNING MANAGER - WAHL VIETNAM CO.,LTD

Manage business relationship with co-workers, stakeholders, suppliers and customers

PROCESS DELEGATE SPECIALIST - BOSCH VN

The Bosch Group is a leading global supplier of technology and services, in the areas of automotive and industrial technology, consumer goods as well as building technology. 

Vietnam to face cement shortage

2014-05-08 16:07:33

Share with friends

The domestic market will probably face a cement shortage in the next 2–3 years if suitable measures are not taken early, industry insiders revealed.

 

According to the Ministry of Construction, the construction industry is anticipated to grow by approximately 7–10% annually in the next few years. Domestic cement consumption this year is expected at approximately 65–67 million tonnes besides around 10 million tonnes for exports.

Though the Prime Minister has so far approved the development plan of the country's cement industry in 2011–20 with a vision to meet the domestic cement demands by 2030, the construction of the approved projects has been slower than scheduled.

Under the development plan, cement plants will churn out 75 million tonnes by 2015 and the figure will increase to 93–95 million tonnes and 113–115 million tonnes by 2020 and 2030, respectively. Between 2012–15, 24 cement production projects totalling a combined output of 24.76 million tonnes per year will be put into operation. The total investment capital of the projects is estimated at nearly VND50 trillion (US$2.38 billion).

However, the implementation of the projects is too slow due to the lack of investment capital.

Due to economic problems, many cement projects, which have been approved in the development plan of the country's cement industry, have failed to kick-start as scheduled due to a shortage of capital. After scrutiny, the government in February had to remove 9 such cement projects.

Tran Van Duong, director of the Government Office's Sectoral Economic Department, noted that the capital to invest in a cement project is very large, especially in equipment purchase.

Duong explained that previously, it was easier for cement project investors to construct cement plants as the government guaranteed them the investment capital for equipment purchase. Currently, the government no longer guarantees such investment, thus most of the cement projects face investment capital shortage.

As some of the approved cement projects have been removed, the country will probably face a shortage of cement in the future if measures are not taken early. It takes at least approximately 3 years to complete the construction of a cement plant under ideal conditions.

To deal with the anticipated shortage, Duong suggested that the Government should continuously scrutinise approved cement projects to remove unsuitable ones and add new and feasible projects to the development plan of the country's cement industry. 

Source: vov